Design, Construction and commissioning of 54MLD capacity sewage treatment plant with activated sludge process with diffused aerators including operation and maintenance for five years in Nesapakkam (Phase-II), Chennai
A 54 MLD capacity sewage treatment Plant of Activated Sludge Process (ASP) with 1 KM of PSC pipeline to Adyar river. The above work was Challange, completed by us. It consists of civil works, Mechanical, Electrical and instrumental works. We have done a gas generation plant for this plant and we convert the sludge to meet have gas and we convert into power about 1MW by an eco-friendly gas engine.
This scheme is the lifeline of Dindukkal, as it is one of the important water supply schemes to serve around 30,000 families of Dindukkal corporation. This scheme, having its water source at Arthur Dam, treats the water at the 17 MLD treatment plant, and through clear water sump, conveying DI pipe mains, booster sumps, feeder mains, overhead tanks at more than 10 locations of size ranging from 1 lakh litre to 10 lakh liter capacity, distributes to the 30,000 house service connections through HDPE & PVC pipes.
Extension of Nemmeli Desalination DI Pipes conveying water main from Medavakkam junction to Alandur Water Distribution station.
This work consists of 800 & 700mm dia DI Pipes & Specials and Pipe carrying bridge.